The contractors who are doing the Symington House landscaping work – Lovell – have finally submitted drawing and timescales of when works will commence around Symington for the landscape works. Work will start at the beginning of July 2012 and is due to finish by the end of August.
The works will take place in four stages
Area Start Date Finish Date
1 02/07/12 03/08/12
(between Symington House and Falmouth Road)
2 23/07/12 17/08/12
(in front of Symington House)
3 06/08/12 31/08/12
(Between the back of Symington House and the Globe Academy)
4 13/08/12 31/08/12
The plan shows the areas referred to above. Download the plan
We have been promised by Lovell that they will keep working space required by contractors to a minimum, so that only 1-2 parking spaces are lost at a time during this period. Symington residents can use other parking spaces on the Lawson Estate, as parking permits cover the whole estate.
We know there will be some inconvenience during this essential works but we hope you will bear with us as the end result will be worth waiting for.
If you have any questions contact the JMB office.